Deploying the Upgrade¶
These are the activities that are performed when the time of deployment comes around. You will need access to a number of resources (Summit, TTS, BTS) at the sites so be sure that you have the credentials to do so. A number of scripts are available for easing the bare metal docker-compose deployment handling. The scripts can be retrieved from this repo: https://github.com/lsst-ts/docker-compose-admin. Use the scripts from the appropriate site directory. If changes are necessary to these scripts from work described in the previous section, use the appropriate site Jira ticket.
Note
The deployment is only concerned with CSCs and systems (Summit, TTS) in the production domain (domainId = 0). All other domains are left alone.
Attention
As the person running the deployment, you have absolute control over the system to complete this process. No one should do anything without your express consent.
Important
Upgrading systems which are controlling hardware, especially the camera CCD, cold, cryo and vacuum systems, needs to be done with care and should be coordinated with the hardware/software experts for those systems.
Log into the machines for bare metal deployments and Kubernetes access (Summit, TTS, BTS)
Use LOVE or Nublado to send all CSC systems to OFFLINE state.
- WARNING: Not all CSCs report OFFLINE; these will instead report STANDBY as the last state seen. Check for heartbeats to be sure. (Summit)
- Preference is to use LOVE, but Nublado is a good fall back in case LOVE isn’t working.
- An overall status view is available from LOVE (Summit, TTS, BTS).
- You can also consult these dashboards on Chronograf. The names are the same across sites.
AT Summary State Monitor
MT Summary State Monitor
EAS Summary State Monitor
Observatory Systems Summary State Monitor
- The Watcher should come down FIRST, to avoid a flurry of alarms going off.
- The ScriptQueues MUST come down last.
With all the systems OFFLINE, you can log out of your Nubaldo instance as we will clean them up soon.
- Once all systems are in OFFLINE, still running CSCs/systems and OSPL daemons need to be cleaned up.
- Get number of currently running daemons/CSCs still in OFFLINE from main OSPL daemon: (Summit, TTS, BTS)
- docker exec ospl-daemon grep “federations” durability.log
- You must give the daemon some time (30 seconds to 2 minutes) before getting worried that the number isn’t going down once you start shutting down daemons.
- You can check this after every shutdown or just periodically.
- Shutdown and Cleanup Bare Metal Deployments (Summit, TTS, BTS).
- Cleanup Kubernetes Deployment.
- Below uses scripts in this repo: https://github.com/lsst-ts/k8s-admin.
- If the script fails, you can use Argo CD to delete the job/deployment/daemonset associated with each application you wish to stop. Be sure to delete the job/deployment/daemonset box not the application itself. Note that auxtel and the other “app of apps” meta applications have no jobs; you have to deal with each application individually.
- Execute the following (Summit (pending k8s deployment), TTS, BTS): ./cleanup_love
- Cleanup Nublado namespaces (Summit, TTS, BTS).
- Below uses a script in this repo: https://github.com/lsst-ts/k8s-admin.
- ./cleanup_nublado
- Check to ensure all daemons have disconnected.
- If the reported number is not 0, you will need to investigate further to find the source of the rogue process.
- Shutdown and Cleanup Main Daemon (Summit, TTS, BTS).
- With everything shutdown, the configurations need to be updated before deployment starts.
- Ensure SQuaRE has approved the
cachemachine
PR and then merge the PR. - Rebase Argo CD branch to single commit, create a PR and merge PR.
- All other configuration repositories should have the necessary commits already on branches and pushed to GitHub.
- Update configuration repositories on bare metal machine deployments (Summit, TTS, BTS).
- Unlike shutdown, only the T&S systems are handled here. DM and Camera are handled by the system principles.
- Also, only certain T&S systems are handled here, the rest need to be coordinated with system principles.
- Ensure SQuaRE has approved the
- Once all configurations are in place, deployment of the new system can begin.
- Be patient with container pulling (goes for everything containerized here).
- Update ESS Controllers (Summit only)
- Update Nublado
- From the site specific Argo CD UI, find the
cachemachine
app. - It should indicate
OutOfSync
(yellow) status, so click theSync
button to begin the process. - Once it syncs, a new pod will start from the
cachemachine
deployment. - The Nublado pull will be completed when the child processes from the new pod all complete and no downstream APIs are shown in the UI.
- From the site specific Argo CD UI, find the
- Startup Minimal Kubernetes Services (TTS, BTS)
- This uses the
sync_apps.py
script found in https://github.com/lsst-ts/argocd-csc/bin. - The script is run in the same place that Kubernetes (kubectl) interactions are run.
- Log into the argocd pod by doing the following:
- python argocd_login.py /path/to/auth_file
- The auth_file must contain the appropriate site username/password on separate lines.
- python sync_apps.py -p –no-sync=love
- csc-cluster-config, ospl-config and ospl-daemon apps will be synced automatically.
- Once the ospl-daemon app is synced, the script will pause.
- Check the logs on Argo CD UI to see if daemons are ready.
- Type
go
and enter to move onto syncing the kafka-producers app. - Script will again pause once the kafka-producers are synced.
- Check that all the logs say “Running” at the bottom. M1M3 now has an indicator saying: “Partial producers are all running”.
- Once all the kafka-producers are verified to be running, stop here but leave the script alive.
- This uses the
- Startup Bare Metal LOVE (Summit, TTS, BTS).
- Continue Kubernetes Deployment
- Go back to where your running
sync_apps.py
script is and typego
and enter to move onto syncing the obssys apps. - Use the Argo CD UI to verify that the containers are pulling and running.
- The script will pause again here. Do not proceed further with the script, but leave it alive.
- Go back to where your running
- Startup Rest of Kubernetes Services.
- Go back to where your running
sync_apps.py
script is and typego
and enter to proceed with syncing the rest of the apps. - The rest of the apps will be synced automatically so no further intervention is necessary.
- Go back to where your running
- Startup Services on Bare Metal Deployments (Summit, TTS, BTS).
- Once the deployment steps have been executed, the system should be monitored to see if all CSCs come up into STANDBY/OFFLINE. Daemons can also be monitored for connection using the methods listed above.
- Use the site specific resources to help ascertain this condition.
- Report any issues directly to the system principles (DMs are OK) to get issue corrected.
- This step is completed when either all CSCs are in STANDBY/OFFLINE or CSCs with issues cannot be fixed in a reasonable (~30 minutes) amount of time.
- If leaving this step with CSCs in non-working order, make sure to report that on the site specific Slack channel.
Certain sites require that some CSCs be put into ENABLED state (Summit, TTS, BTS).
- The following additional services also need to be synced after a Cycle upgrade.
- schedview (Summit)
- rubintv-broadcasters (Summit and TTS)
If not carrying on with integration testing, folks can be told they can use Nublado again via the site specific Slack channel.